India has substantially increased public capital expenditure to strengthen infrastructure, connectivity and economic productivity. The Union Budget 2026–27 provides ₹12.22 lakh crore for capital expenditure. However, greater allocations do not automatically result in more completed and functioning infrastructure. The Ministry of Statistics and Programme Implementation (MoSPI) reported 1,775 ongoing central-sector infrastructure projects costing ₹150 crore or more in July 2026, with an aggregate revised cost of ₹37.11 lakh crore and cumulative expenditure of ₹19.26 lakh crore. These figures demonstrate the scale of ongoing investment, although expenditure remaining on unfinished projects should not be confused with cost overruns. Evidence from Mumbai Metro Line 3, Dedicated Freight Corridors and national highway projects highlights the importance of project preparation, interagency coordination, execution and commissioning. Tatvita proposes an Infrastructure Execution and Accountability Framework (IEAF) to strengthen project readiness, assign institutional responsibilities, establish early-warning mechanisms and verify operational outcomes. The central policy recommendation is to move beyond monitoring expenditure towards measuring how efficiently committed public capital becomes completed, functioning infrastructure that delivers economic and social benefits. The Infrastructure Spending Paradox: More Investment, But How Much Completed Infrastructure? India’s infrastructure strategy increasingly relies on public capital expenditure to strengthen long-term economic growth. Investments in roads, railways, logistics, energy and urban infrastructure are expected to reduce transaction costs, improve connectivity, attract private investment and raise productivity. The Union Budget 2026–27 allocated ₹12.22 lakh crore for capital expenditure, approximately 3.1% of GDP. The effective capital expenditure, including grants for creating capital assets, was estimated at ₹17.15 lakh crore. […]